Central Water Reclamation Facility BioSolids Building

Photo of Central Water Reclamation Facility BioSolids Building

Emerald Coast Utilities Authority

Pensacola, FL

HMM was responsible for the design of a CMU block building with metal truss and standing metal seam roof to house an initial 30 dry ton/day capacity Class AA biosolids treatment and handling facility at the Emerald Coast Utilities Authority’s new 22.5 MGD Central Water Reclamation Facility. The building has approximately 12,000 sqft of process floor space with an additional 4,700 sqft of ancillary equipment and office space.

Project Highlights

  • Floor space for two steam paddle driers, six duplex screw presses, water conditioning and boiler rooms, chemical and polymer storage and feeds and MCC room
  • Mezzanine level with offices overlooking process floor with storage and restrooms
  • Overhead travel crane for working floor
  • Explosion blowout panels
  • Florida Building Code hurricane design compliant